BD Medical
Details:
The demolition, alteration and extension to the existing Workshop Building to form a new Production Facility and a Fit-Out of the existing warehouse mezzanine floor with new staff changing rooms, toilets, kitchen, canteen and office space as part of the enabling works for the new Front End Development Project. Value:
€2.2 Million Engineers / Architects:
DMOD Completion:
2015
BMS Swords
Details:
Civil & Structural works in connection with the removal & replacement of cooling towers, within a live operating facility and adjacent to existing operations. Works included: piling, concrete pad foundations, drainage alterations, new support steelwork frame, new gantries, stairs and access platform, erection of temporary tower crane including piled foundation and base, new concrete hard standings and significant scaffolding support system for the duration of the works. Value:
€700K Engineers / Architects:
DPS Engineering Completion:
2015
Dia Sorin Ireland Ltd
Details:
This project involved the refurbishment and fit-out of an existing two story office building. It was completed in twelve weeks and included full mechanical and electrical services as well as high specification laboratory furniture and fittings. Value:
€1 million Engineers / Architects:
McElroy & Associates Completion:
2014
Mallinckrodt
Details:
This project involved the construction of a new development/containment laboratory with associate lobbies within an existing live facility. The work involved Civils, Mechanical, Electrical and Fire Protection works within the building, as well as new laboratory furniture and equipment, internal and roof platforms for M&E plant. Value:
€700K Engineers / Architects:
McElroy & Associates Completion:
2014
Rottapharm Ltd
Details:
This project involved the construction of a new metal cladded, steel framed building, within the confines of an existing live production facility. It also involved the Mechanical, Electrical and Fire Protection works within the building and the Mezzanine Flooring, partitions, wall floor and ceiling completions and finishes. Value:
€1.8 million Engineers / Architects:
McElroy & Associates Completion:
2014
National Rehabilitation Hospital
Details:
Conversion of Existing Vacant Rooms to state of the art hospital ward. Value:
€750K Engineers / Architects:
Adam Hall Architecture Completion:
2013
Helsinn Birex Pharmaceuticals Ireland Ltd
Details:
Laboratory & Office Fit-Out Value:
€1.34 million Engineers / Architects:
McElroy & Associates
Helsinn Birex Pharmaceuticals Ireland Ltd
Details:
OSD Facility Value:
€2.2 million Engineers / Architects:
DPS Engineering
Servier Industries (Ireland) Ltd
Details:
Chemical Manufacturing Building Value:
€5 million Engineers / Architects:
Peter Legge & Associates
Schering Plough (Avondale) Company, Rathdrum
Details:
Partial Schering Plough Project Value:
€5m to €25m Engineers / Architects:
McElroy & Associates
Schering Plough (Avondale) Company
Details:
P2 P3 P4 Expansion Value:
€24m Engineers / Architects:
DPS Engineering and McElroy Associates
Baxter Healthcare Deansgrange
Details:
Cleanrooms, Warehouse & Offices Value:
€6m Engineers / Architects:
Duffy Mitchell Architects
National Rehabilitation Hospital Dun Laoghaire
Details:
Various projects in National Rehabilitation Hospital Value:
€500K - €8m Engineers / Architects:
Duffy Mitchell Architects & NRH
Client: St. Patrick's Missionary Society
Details:
Nursing Care Units Value:
€3 million Engineers / Architects:
Coughlan Dekeyser Associates